Christ Church Episcopal School in Greenville broke ground on a $56 million campus expansion on Nov. 17.
The groundbreaking ceremony marks the start of the first phase of the private school’s “Build for the Future” Campus Master Plan. David Padilla, head of school at Christ Church Episcopal School, said it is a transformational project both for the school and the entire Greenville community.
“Build for the Future renews our promise to deliver an education that is innovative, rigorous and rooted in character — and it does so in spaces where students of all ages can think boldly, collaborate deeply and feel a profound sense of belonging,” Padilla said.
Christ Church Episcopal School’s board of trustees launched a comprehensive planning process for the school’s campus at 245 Cavalier Drive in 2021. This effort resulted in a multiphased, long-range campus master plan to address the private school’s immediate and future needs.
Phase one of the “Build for the Future” Campus Master Plan includes building the Technology, Innovation, Design and Entrepreneurship Center, also known as the TIDE Center. The new 22,000-square-foot building will feature classrooms, learning labs, an outdoor learning space, breakout rooms, a conference room, a grab-and-go cafe, and other flexible learning spaces.
“Coming off of 2020 and COVID-19, I think that we learned a lot of lessons about flexible spaces and outdoor areas,” said Sarah Beasley, campaign co-chair. “So I think that a lot of this plan has to do with more area to educate the children and safety if we ever have that situation again.”
A 56,000-square-foot Sports Performance Building will also be built during the master plan’s initial phase. The facility will include a competition gymnasium, strength and conditioning space, wrestling practice space, a dedicated training center, locker rooms, an elevated indoor track and more. A new lacrosse and field hockey field, and an additional practice field will also be constructed as part of the project.
Padilla explained that the “Build for the Future” Campus Master Plan also aims to address the campus’s infrastructure needs. For example, a new loop road will be added in phase one to create a pedestrian-centered campus and help pull traffic off Cavalier Drive and Wenwood Road. Additional parking will also be constructed on the campus.
Christ Church Episcopal School launched a $40 million fundraising campaign to help pay for phase one of the campus expansion project. So far, $27 million has been raised from private donations. Padilla said the school is on track to reach the fundraising goal by December 2026. The project’s remaining cost will be covered by long-term debt.
“Our community dreamed big – and then rolled up our sleeves,” said Katie Howell, campaign co-chair. “The generosity and partnership behind this campaign reflect the best of CCES and the Upstate: vision, momentum, and a shared belief that when we invest in students, everyone benefits.”
McMillan Pazdan Smith Architecture, Brasfield & Gorrie and LCK are partnering to complete the project. Construction of the master plan’s initial phase is expected to take 18 to 20 months to complete. Padilla said the new facilities will be open by the fall of 2027.
For more information, visit cces.org/about/build-for-the-future-campus-master-plan/our-campus-plan.
Expanded footprint
Christ Church Episcopal School acquired 22 additional acres of land along Mauldin Road as part of the “Build for the Future” Campus Master Plan. This land acquisition increased the school’s campus from 72 acres to 94 acres.