Drivers who regularly brave the congested traffic of Woodruff Road will have to wait years to see improvements.
The $121 million Woodruff Road Congestion Relief Project, spearheaded by the South Carolina Department of Transportation, is on track to begin construction in 2026, with a completion date set for 2029, according to representatives with SCDOT.
But that’s only if everything falls into place, said Pete Poore, SCDOT director of communications, during a public meeting held April 5 at Belk Academy on Woodruff Road.
“The intent then is to start purchasing property next year, around the spring of 2023, and if everything goes right, construction will begin in 2026 and the project will be finished in 2029,” Poore said.
The purpose of the project is to minimize traffic congestion and improve public safety on the busiest commercial area of Woodruff Road, between I-385 and Roper Mountain Road/Verdae Boulevard, where traffic volumes reach more than 40,000 vehicles per day.
The worst hours, as most drivers know, are in the morning, during lunchtime and during rush hour in the early evening. Uniquely, due to the high volume of commercial activity, the midday peak is often higher than the evening peak.
See the full plans for Woodruff Road

The so-called “Preferred Alternative” plan from SCDOT aims to create a new, 5-lane alternative route parallel to Woodruff Road extending from Verdae Boulevard to the intersection of Smith Hines and Woodruff roads. The new roadway would consist of four travel lanes with a median and pedestrian safety improvements that include a sidewalk, a multi-use path and two new bridge crossings at I-85 and I-385.The plan also calls for improving numerous intersections and access points along Woodruff Road.
Collateral impact:
- 22 commercial units may have to be relocated
- 3 hazardous materials sites will be removed
- 0.9 acres of floodplain will be removed
- 1,498 linear feet of streams will be removed
- 0.13 acres of wetlands will be removed
- 46 acres of right-of-way will be acquired
Public comment on the plans can be made online from now until April 28, and comments will be reviewed by the project team in May and June.